DHA Approval for Clinic Fit-Out in Dubai: A Step-by-Step Guide
DHA Approval for Clinic Fit-Out in Dubai: A Step-by-Step Guide
A clinic in Dubai cannot open until the Dubai Health Authority (DHA) has approved its design and inspected the finished facility. That health approval sits alongside the landlord, Dubai Municipality and Civil Defence approvals for the fit-out itself, so the clinic design has to satisfy all of them at the same time.
This guide walks through the DHA approval process for a clinic fit-out step by step, explains where each approval fits in the project, and lists the design points that most often cause delays. It is written for clinic owners, medical directors and investors planning a new clinic or relocating an existing one.
Which Authority Licenses Your Clinic?
Most clinics in Dubai are licensed by DHA. Clinics inside Dubai Healthcare City are licensed by the Dubai Healthcare City regulator instead, so the first step is to confirm which health regulator covers your unit.
The fit-out permit for the building works is a separate approval. It comes from the authority that covers the building, for example Dubai Municipality on the mainland or a free zone authority, and fire and life safety design is reviewed by Civil Defence. Our authority approvals page explains how location decides the approving authority.
How the DHA Facility Approval Works
DHA handles health facility approvals online through the Sheryan portal, using two applications:
- New Facility Licence Application: the facility design is submitted and reviewed against the DHA Health Facility Guidelines. If the design complies, DHA issues the facility licence.
- Activate Facility Licence Application: once construction and commissioning are complete, DHA inspects the facility before the licence is activated and the clinic can operate.
For non-hospital facilities such as clinics, the design is usually submitted as one detailed submission. Hospitals must follow a two-step route, with a schematic design first and a detailed design second.
DHA Clinic Fit-Out Approval: Step by Step
1. Define the clinic type and services
The specialities you offer decide which rooms the clinic needs and the standards each room must meet. A general practice, a dental clinic and an aesthetic clinic with procedure rooms have very different requirements, so the service list should be fixed before design starts.
2. Secure the unit and the landlord NOC
Check that the building can support a healthcare use, including air conditioning and electrical capacity, water and drainage points, and accessible access. The landlord will need to approve the design and issue an NOC before authority submissions.
3. Design to the DHA Health Facility Guidelines
The clinic is designed to the DHA Health Facility Guidelines, which set out the architectural requirements for each type of room and the engineering standards for building services. The design also has to follow the Dubai Universal Design Code for accessibility, the UAE Fire and Life Safety Code of Practice, and the Al Sa’fat green building system. DHA guidance refers to prequalified design consultants preparing and submitting these plans.
4. Submit the New Facility Licence Application
The detailed design is submitted on Sheryan. It covers the architectural layout and the engineering design, including services such as medical gases, nurse call systems and medical equipment where the clinic needs them, together with the supporting design reports.
5. Obtain the other authority approvals
Before construction starts, the fit-out permit, Civil Defence approval and any other authority approvals must be in place. DHA does not check these approvals for you, so they need to be planned in parallel with the health approval.
6. Build exactly to the approved design
The clinic must be built to the DHA-approved design. Any change needs a new DHA approval before it is built, and DHA inspectors cannot approve changes made on site. This is why layout decisions should be final before the design is submitted.
7. Pre-inspection and final inspection
When construction is complete and the services are commissioned, the Activate Facility Licence Application is submitted. A pre-inspection assessment can be requested at completion to list items to fix, followed by the final inspection. At this stage DHA also needs the licence details and the healthcare professionals who will work in the clinic.
8. Licence activation
DHA inspection results are graded, from approval through approval with conditions to suspension or rejection. Once the facility passes, the licence is activated and the clinic can open.
Where Each Approval Fits in a Clinic Fit-Out
| Project stage | What happens | Who is involved |
|---|---|---|
| Brief and concept | Services, room list, patient flow and concept design | Clinic owner, medical director, designer |
| Detailed design | Layout and engineering design to DHA guidelines | Designer, engineers |
| Health approval | New Facility Licence Application on Sheryan | DHA, or the Dubai Healthcare City regulator |
| Building approvals | Landlord NOC, fit-out permit, fire and life safety approval | Landlord, Dubai Municipality or free zone authority, Civil Defence |
| Construction | Fit-out built to the approved drawings | Fit-out contractor |
| Commissioning | Testing of air conditioning, electrical and medical services | Contractor, specialist suppliers |
| Inspection and licence | Pre-inspection, final inspection and licence activation | DHA |
Design Points That Commonly Cause Delays
Most approval delays come from details that are hard to change once walls are built. The points below are worth checking with your designer before the design is submitted:
- Room sizes and clearances that do not meet the guideline for that room type
- Patient, staff and clean and dirty flows that cross each other
- Missing or badly placed hand-wash basins
- Wall, floor and ceiling finishes that are not easy to clean
- Accessibility for wheelchair users at the entrance, toilets and treatment rooms
- Air conditioning and ventilation that do not suit treatment or procedure rooms
- Changes made on site without a revised approval
How We Approach Clinic Interior Design and Fit-Out
We design and fit out clinics in Dubai with these requirements built into the layout from the start, so approval comments are dealt with on paper rather than on site. Our clinic interior design service covers space planning, finishes, lighting, bespoke furniture and the fit-out works, and we coordinate the drawings, NOCs, permits and inspections for the approvals we manage.
Clinic projects are part of our wider interior fit-out services in Dubai. For beauty-led spaces such as salons and spas, see our salon interior design page.
Frequently Asked Questions
Do I need DHA approval before starting a clinic fit-out?
Yes. Under the DHA process, the facility design is submitted through the New Facility Licence Application on the Sheryan portal and approved before construction. Dubai Municipality, Civil Defence and landlord approvals are also needed before work starts on site.
Can I change the clinic layout during construction?
Not without approval. DHA guidance says the clinic must be built to the approved design, changes need a new DHA approval before they are built, and inspectors cannot approve changes on site.
Is Dubai Healthcare City licensing the same as DHA?
No. Clinics inside Dubai Healthcare City are licensed by the Dubai Healthcare City regulator rather than DHA, so check which regulator covers your location before you start the design.